This page last changed on Jan 29, 2008 by jbirch.

 Outline of instrument plan for Jan-Jun, 2008

Mack has been cold tested with new hand and new valves and Roman Flush run to check tubing.

Temp calibration Jan 29-31.

Feb 5,6,7 Science will prep reagents, generate mission script, run sub-protocol tests 

  1. One month cold test of Mack w/ his new valves/hand starting Feb 11.
    1. OBJECTIVE:  get through a full carousel of pucks
    2. test should last most of 4 weeks (although 3 weeks would be acceptable)
  2. March 3 is earliest we pull and deem a success.  Once pulled, we replace with Bruce in chamber. 
  3. Prep for Spring deployments (Mar 26-->Mar 27)
  4. Deploy MACK (April 1-Shana Rae)
    • Cold test Bruce (Mar 17 - Mar 28) and Neo (Mar 31 - Apr 11)
  5.  Recover MACK, Deploy BRUCE (May 1)
  6. Recover BRUCE (May 27), Deploy both MACK and NEO (May 28)
  7. End mission Jun 30.





(Revised 29 Jan 2008) 

Document generated by Confluence on Feb 03, 2026 14:16