|
This page last changed on Jan 29, 2008 by jbirch.
Outline of instrument plan for Jan-Jun, 2008
Mack has been cold tested with new hand and new valves and Roman Flush run to check tubing.
Temp calibration Jan 29-31.
Feb 5,6,7 Science will prep reagents, generate mission script, run sub-protocol tests
- One month cold test of Mack w/ his new valves/hand starting Feb 11.
- OBJECTIVE: get through a full carousel of pucks
- test should last most of 4 weeks (although 3 weeks would be acceptable)
- March 3 is earliest we pull and deem a success. Once pulled, we replace with Bruce in chamber.
- Prep for Spring deployments (Mar 26-->Mar 27)
- Deploy MACK (April 1-Shana Rae)
- Cold test Bruce (Mar 17 - Mar 28) and Neo (Mar 31 - Apr 11)
- Recover MACK, Deploy BRUCE (May 1)
- Recover BRUCE (May 27), Deploy both MACK and NEO (May 28)
- End mission Jun 30.
(Revised 29 Jan 2008)
|